Photos I

| Home | Photos II | Photos III |

February 2004

The preparation for replacing our 1920's basement began in May 2003. Nine months later, demolition and construction began.

 

Monday, February 16

Pouring rain & standing water. Six men arrived around 8am.

Removing the back chimney

NW Corner

Cribs are the stacks of wood that hold the beams & jacks

NE Corner

Lifting a beam off the trailer

Leveling and tightening the beam. (Blue at top of picture is my umbrella)

Beam near front chimney (you can see all the way to back of house)

Inside view, SW corner

Inside view, NE corner & near where stairs once were

 

Tuesday, February 17

MOVING UP

This is the only section without the basement below

Placing beams in the NW corner of the house

A jack in the SW corner

1 of 4 jacks that lift the beams that support the house!

Chimney

This is the motor that drives the pump that pressurizes the jacks that lifts the house (estimated at 150,000 pounds!)

While 1 person mans the motor, 3 remain under the house and 2 others are outside - all monitoring the process

North side

NW Corner

North & West sides

South Side

The house is raised in increments

(4 times). After achieving a certain height, cribs are shored up with additional 6" x 8" x 4' timbers and jacks are adjusted.

SW Corner (front)

SE Corner (back)

NW Corner (front)

Back of house

 

March 1 - 5

EXCAVATION

Breaking up concrete walls & floor

Monday

North Side

Backhoe moving concrete chunks

View from inside & underneath

Digging out the concrete floor using a jackhammer (attached to bobcat)

Tuesday

East end

South side; stairs are almost out

SW Corner

 Thursday

Back

NE Corner

Driveway (a.k.a. mudway)

View from across the street

Friday

 Laying gravel down

Moving & excavation by . . .

NW Structural Moving

 

March 8 - 12

Tuesday

Removing debris, dirt, & concrete from the driveway

Now it's time to rebuild . . .

 

FOOTING FORMS

View from back; forms are in place for footings (wall foundation)

Front

The red tubing is a plastic cover over a copper tube (furnace oil line)

The section without rebar marks one of two outside doors

Water & sewer pipes

Jerry (plumber) came over on Saturday to move sewer and water pipes

Pipes were redirected to what will be the inside of the new walls

 

March 15 - 19

CONCRETE FOOTINGS

Tuesday

SE Corner

Front

It's a tough job watching the concrete slide down the chute

View from front

Wednesday

Removed forms and raised house an additional foot

 

March 22 - 24

WALL FORMS

Monday

South side

Interior (south side)

North side

Interior (north side)

Interior (towards front SW corner)

Tuesday

North side . . . note window frames

South side . . . section to left framed on both sides

East side top view

 

March 25 - 26

CONCRETE WALLS

Thursday

2 trucks and a pump

Concrete is pumped through the black hose

One keeps it flowing; another pounds on the plywood; two others use a machine to move it to the desired location

Top of the south wall

Friday

North side

South side

March 29 - April 2

TRENCHES

Thursday

Trench to the culvert running along the street

Drilling into the culvert

The plug that was drilled out

Laying pipes that will connect to rain drains around basement foundation

Trench for electrical conduit and Steve (electrician)

Jerry (plumber) laying copper tubing for water line

Work by . . .

Bruce Konell Excavation

Horton Electric

Sasse Plumbing

 

Top of Page

April 5 - 9

Tuesday

Filling holes with tar

Next, two layers of heated tar is sprayed below grade

Fiberglass panels in place

Work by . . .

 Jim Dowers Waterproofing

 

Wednesday

Perforated pipes for footing drains & ABS pipe for downspout drains

South side

Drainage rock

Dumping rock over pipes

 

April 19 - 23

BACKFILL

Thursday

Breaking up old well casing

Filling wheelbarrows

Dumping dirt around basement perimeter

South side; well casing gone and section dug out for stairs

North Side

East side; section dug out for stairs

Friday

Prep work on underside of house (shimming, fixing dry rot...)

 

April 26 - 30

Monday

Conveyer belt shoots gravel inside through window frames

Leveling out gravel piles (rock is entering on right side)

Base of front porch

East stairs (retaining walls)

Framing retaining walls for south stairs in 86o weather

 

COMING DOWN

Wednesday

Same process in reverse, with much better weather!

NE Corner

South Side

NW Corner

Shimming up chimney from both sides (by ladder)

Dangling electrical wiring & temporary supports down the middle

SW Corner

NE Corner

Beams are pulled out and hauled away

North side

Leveling and shimming chimney

Keith makes it all look so easy

For Comparison

 

Before & After Lift

 

New Walls & Back Down

 

Thursday - Friday

Jaime & I put in the (black ABS) ground drainage . . . (red covered copper tubing is for heating oil)

Remaining crib materials were removed

Rock was leveled out

Also . . .
bullet

Concrete was poured for stair walls, front porch base, and perimeter wall patching (where beams were lowered)

bullet

Materials were dropped off for center & side beam, as well as supporting posts

 

May 24 - 28

Wednesday

 eDay 100f

Electrical box and panel

Friday

Brian, Keith, & company

Concrete for stairs (east side)

South side

2 sets of stairs

At the base is a covered drain

Inside stairs . . . yahoo!

 

May 31 - June 6

Wednesday - Sunday

PGE made their connections

Bathroom partly framed

Our 10 year old furnace in place

New oil water heater

Thundershowers with some of the heaviest rain I have EVER seen!

 June 7 - June 11

Tuesday

Steve making ducts & Peter installing ductwork below

Work by . . .

First Call Heating & Cooling

Re-leveling the mudroom & installing posts

Hauling away the dirt . . .

Spreading gravel

We have our driveway back!

Friday

Ductwork above bathroom

Kevin

North side (plumbing for washer/dryer, bathroom, hot water heater)

South side sink

Washer/dryer hookups

June 13 - June 19
bullet

Passed plumbing inspection, but had trouble with electrical inspection L

bullet

Completed HVAC

bullet

Connected washer & dryer

bullet

Installed windows

bullet

Moved back into house on Friday in 90o heat

 

June 20 - June 26
bullet

Mom moved back into her place on Sunday

bullet

Water meter replaced (Monday)

bullet

Front chimney base partly repaired (Tuesday)

bullet

Exterior doors & electrical wiring

bullet

Underground sprinklers can now be operated manually, but line that runs across driveway is broken L

 

June 27 - July 10

Took a big load of construction "junk" to the dump so we temporarily have the patio back.

Also, the cats love the catwalk that Jaime built (so they can use the pet door)

Doors & windows on east and south sides

Temporary set-up of washer/dryer
bullet

Reconnected Vacuflo to main floor

bullet

Reconfigured and connected 6 of 13 intercom stations

 

 July 11 - 31

Not much happening

 

August  (dog days of summer)
bullet

Completed the electrical work for the feeder & passed inspection

 

September
bullet

Some interior framing

bullet

Concrete & rock areas around perimeter

 

October - December
bullet

Looking into options for new windows, gutters, and fixing the damaged &/or missing siding

bullet

Patching interior cracks & painting

bullet

Waiting for Ted to begin work on front & back porches

 

 

Click here for the next page.