February 2004 The preparation for replacing our 1920's basement began in May 2003. Nine months later, demolition and construction began.
|
||||||||||||||||||||||||||||||||||||||||||
|
Monday, February 16 Pouring rain & standing water. Six men arrived around 8am. Removing the back chimney NW Corner Cribs are the stacks of wood that hold the beams & jacks NE Corner Lifting a beam off the trailer Leveling and tightening the beam. (Blue at top of picture is my umbrella) Beam near front chimney (you can see all the way to back of house) Inside view, SW corner Inside view, NE corner & near where stairs once were
Tuesday, February 17 MOVING UP This is the only section without the basement below Placing beams in the NW corner of the house A jack in the SW corner 1 of 4 jacks that lift the beams that support the house! Chimney This is the motor that drives the pump that pressurizes the jacks that lifts the house (estimated at 150,000 pounds!) While 1 person mans the motor, 3 remain under the house and 2 others are outside - all monitoring the process North side NW Corner North & West sides South Side The house is raised in increments (4 times). After achieving a certain height, cribs are shored up with additional 6" x 8" x 4' timbers and jacks are adjusted. SW Corner (front) SE Corner (back) NW Corner (front) Back of house
March 1 - 5 EXCAVATION Breaking up concrete walls & floor Monday North Side Backhoe moving concrete chunks View from inside & underneath Digging out the concrete floor using a jackhammer (attached to bobcat) Tuesday East end South side; stairs are almost out SW Corner Thursday Back NE Corner Driveway (a.k.a. mudway) View from across the street Friday Laying gravel down Moving & excavation by . . .
March 8 - 12 Tuesday Removing debris, dirt, & concrete from the driveway Now it's time to rebuild . . .
FOOTING FORMS View from back; forms are in place for footings (wall foundation) Front The red tubing is a plastic cover over a copper tube (furnace oil line) The section without rebar marks one of two outside doors Water & sewer pipes Jerry (plumber) came over on Saturday to move sewer and water pipes Pipes were redirected to what will be the inside of the new walls
March 15 - 19 CONCRETE FOOTINGS Tuesday SE Corner Front It's a tough job watching the concrete slide down the chute View from front Wednesday Removed forms and raised house an additional foot
March 22 - 24 WALL FORMS Monday South side Interior (south side) North side Interior (north side) Interior (towards front SW corner) Tuesday North side . . . note window frames South side . . . section to left framed on both sides East side top view
March 25 - 26 CONCRETE WALLS Thursday 2 trucks and a pump Concrete is pumped through the black hose One keeps it flowing; another pounds on the plywood; two others use a machine to move it to the desired location Top of the south wall Friday North side South side March 29 - April 2 TRENCHES Thursday Trench to the culvert running along the street Drilling into the culvert The plug that was drilled out Laying pipes that will connect to rain drains around basement foundation Trench for electrical conduit and Steve (electrician) Jerry (plumber) laying copper tubing for water line Work by . . .
|
April 5 - 9 Tuesday Filling holes with tar Next, two layers of heated tar is sprayed below grade Fiberglass panels in place Work by . . .
Wednesday Perforated pipes for footing drains & ABS pipe for downspout drains South side Drainage rock Dumping rock over pipes
April 19 - 23 BACKFILL Thursday Breaking up old well casing Filling wheelbarrows Dumping dirt around basement perimeter South side; well casing gone and section dug out for stairs North Side East side; section dug out for stairs Friday Prep work on underside of house (shimming, fixing dry rot...)
April 26 - 30 Monday Conveyer belt shoots gravel inside through window frames Leveling out gravel piles (rock is entering on right side) Base of front porch East stairs (retaining walls) Framing retaining walls for south stairs in 86o weather
COMING DOWN Wednesday Same process in reverse, with much better weather! NE Corner South Side NW Corner Shimming up chimney from both sides (by ladder) Dangling electrical wiring & temporary supports down the middle SW Corner NE Corner Beams are pulled out and hauled away North side Leveling and shimming chimney Keith makes it all look so easy For Comparison
Before & After Lift
New Walls & Back Down
Thursday - Friday Jaime & I put in the (black ABS) ground drainage . . . (red covered copper tubing is for heating oil) Remaining crib materials were removed Rock was leveled out Also . . .
May 24 - 28 Wednesday eDay 100f Electrical box and panel Friday Brian, Keith, & company Concrete for stairs (east side) South side 2 sets of stairs At the base is a covered drain Inside stairs . . . yahoo!
May 31 - June 6 Wednesday - Sunday PGE made their connections Bathroom partly framed Our 10 year old furnace in place New oil water heater Thundershowers with some of the heaviest rain I have EVER seen! June 7 - June 11 Tuesday Steve making ducts & Peter installing ductwork below Work by . . . First Call Heating & Cooling Re-leveling the mudroom & installing posts Hauling away the dirt . . . Spreading gravel We have our driveway back! Friday Ductwork above bathroom Kevin North side (plumbing for washer/dryer, bathroom, hot water heater) South side sink Washer/dryer hookups June 13 - June 19
June 20 - June 26
June 27 - July 10 Took a big load of construction "junk" to the dump so we temporarily have the patio back. Also, the cats love the catwalk that Jaime built (so they can use the pet door) Doors & windows on east and south sides Temporary set-up of washer/dryer
July 11 - 31 Not much happening
August (dog days of summer)
September
October - December